9609 Business November 2025 Question Paper 33

Source PDF on the left, extracted YAML on the right. Compare numbering, marks, options and text.

3 short_answer

3 (a) Using the data in Table 1.1, calculate the payback period [2]

(b) Using the data in Table 1.1, calculate the net present value (NPV) over six years discounted at 8% [2]

(c) Evaluate LBM’s decision to go ahead with the hot water mine , , [12] , ,

3a 8 marks calculation 10.3
3b 2 marks calculation 10.3
3c 2 marks calculation 10.3
2 8 marks long_answer

2 Analyse one benefit and one limitation of sales forecasting to LBM as it begins its mining operations [8] , ,

1 12 marks calculation

1 Analyse two advantages to the government of country G that could result from the nationalisation of LBM [8] , ,

4 short_answer

4 (a) Using Figure 1.1:

(i) calculate the total float for activity C [3]

(ii) identify the minimum project duration [1]

(b) Evaluate the importance of Critical Path Analysis (CPA) to the success of the hard rock mine , , [12] , ,

4a short_answer
4ai 3 marks calculation 9.3
4aii 1 mark calculation 9.3
4b 12 marks calculation 9.3